Ballou
Jr High School, Building 100 Rebuild
9916 - 136th Street East
Puyallup, WA
Contract
$: 2,680,000
Contract
Date : December 2000
Completion Date: July 2001
33% of work self performed
Owner
Reference:
Puyallup School District #3
David Johnson, 253.840.8831
Architect:
BLRB
Mike Reynolds, 253.627.5599
|
|
This
was a new building project built on a campus that was fully
occupied by staff, general public, and students. Building 100
originally burned to the ground in 2000. The owner, after resolving
with the insurance entities involved, proceeded with the replacement
of the building, with a new, upgraded design.
This
fast track project started in February, 2001. After initial
demolition of existing, remaining concrete slabs and footing
systems, the project suffered a three week permit delay. BNCC,
on its own accord, changed its pre-planned sequence of construction,
and brought the project back onto the "original as planned
schedule". The project was done on time and within owner
budgets.
|